同工程界嘅朋友傾起BIM,好多時都會出現以下嘅對話﹕
"單嘢LOD畫幾多?"
"有幾多個clashes? Solve晒未?要零clashes喎。"
"係唔係要做埋5D, 6D, 7D, 8D…?"
如果對BIM嘅認識仲停留响上述講法,就係時候要更新一下。
先講LOD。筆者於前文<Conceal Conduit需唔需要BIM>已提及過,早於CIC MEP BIM Standards (2019 version),已經將LOD分拆成 LOD-Graphic (LOD-G) , LOD-Information (LOD-I) 及 DOC。LOD-G係先係描述緊個elements要model到有幾細緻,如圖﹕
而LOD-I,係描述緊個element嘅資料有幾詳盡,如圖﹕
DOC 係 Level of Documentation,即係個 BIM 嘅 DOC 應該包括埋 Catalogue, O&M Manual, Test Report, Warranties, Statutory…etc., 如圖﹕
即使係去到As-Built Stage,CIC MEP BIM Standards (2019 version) 只建議 LOD-G 去到300。最主要係考慮到modelling太多細節位的話,個BIM file size會好大,好多電腦硬件行唔到;當然,LOD-I 就建議去到500。所以,以後大家講LOD嘅時候,最好講清楚係LOD-G or LOD-I。
站於Client PM嘅角度,佢地好多時對LOD-G畫到有幾精細係唔會太關心,只要件嘢畫出嚟大概分辨到係啲乜就得;佢地真正關心嘅係件嘢係唔係跟足approved嘅物料嚟畫、畫得齊唔齊(如congested area嘅hangers)、夠唔夠空間運送、安裝及維修等等;至於LOD-I,就真係要入資料入得足,因為日後FM嘅同事真係要用到。
至於clashes方面,一般 Consultancy Agreement 或 Main Works Contract 的確係會寫死”Clashes Free” or “Zero Clashes”。至於撞5mm算係一個clashes,定係50mm先算係?暫時香港或國際用開嘅Standards or Guidelines都冇定義過,普遍做法會set 25mm ~ 50mm 之間。但站於工程項目PM嘅角度,佢地關心嘅唔係clashes個數字,而係落到場啲嘢係唔係真係夠位裝、夠位日後maintenance。筆者認為比較好嘅做法係,為呢堆clashes嘅重要程度分類,如下表﹕
DevB TC 2020年開始嘅BIM KPI,都只係以BIM Uses嚟劃分﹕ 一般嚟講,合約BIM Specification嘅BIM Uses會寫到好虛,舉一例,第14項 BIM Uses 嘅 3D Control and Planning,一般會咁寫﹕
"For a large-scale project requiring Digital Works Supervision System, the Contractor shall utilize the BIM model for digital setting-out, construction checking, etc. as appropriate by means of 3D laser scanners, robotic total stations, etc. as far as practicable."
究竟個3D laser scanners要點用法?全個地盤任何setting out,包括開大墨、裝地渠、釘板留窿、砌牆...等等都要用?As far as practicable應該點理解?一個地盤咁多個位同時做緊嘢,而一台機幾十萬又要有受過專業訓練嘅人先識用,要求判頭成個地盤都用3D laser scanners又合唔合理? 抑或用嚟覆核一次墨斗哥哥條數已經算係做到呢個BIM Uses?
呢個時候,就係BIM Execution Plan BEP出場嘅時間。業主、顧問、判頭,可以基於地盤實際嘅需要,由判頭於BEP提出實現呢項BIM Uses嘅詳盡方法及應用範圍,然後上比顧問做approval,而呢份BEP就會以新嘅合約形式出現 (舊嘅合約係BIM Specification,新嘅合約係BEP;BEP係基於BIM Specification嘅原則而制定)。當然,BEP係一份 living document [1] 嚟,業主或顧問可以跟據實際情況要求判頭更新該文件並再次提交審批。
[1]: Living document is a document that is continually edited and updated.