2024年5月25日星期六

工程合約BIM要求 - 高手只關心BIM USES

同工程界嘅朋友傾起BIM,好多時都會出現以下嘅對話﹕ "單嘢LOD畫幾多?" "有幾多個clashes? Solve晒未?要零clashes喎。" "係唔係要做埋5D, 6D, 7D, 8D…?" 如果對BIM嘅認識仲停留响上述講法,就係時候要更新一下。 先講LOD。筆者於前文<Conceal Conduit需唔需要BIM>已提及過,早於CIC MEP BIM Standards (2019 version),已經將LOD分拆成 LOD-Graphic (LOD-G) , LOD-Information (LOD-I) 及 DOC。LOD-G係先係描述緊個elements要model到有幾細緻,如圖﹕ 而LOD-I,係描述緊個element嘅資料有幾詳盡,如圖﹕ DOC 係 Level of Documentation,即係個 BIM 嘅 DOC 應該包括埋 Catalogue, O&M Manual, Test Report, Warranties, Statutory…etc., 如圖﹕ 即使係去到As-Built Stage,CIC MEP BIM Standards (2019 version) 只建議 LOD-G 去到300。最主要係考慮到modelling太多細節位的話,個BIM file size會好大,好多電腦硬件行唔到;當然,LOD-I 就建議去到500。所以,以後大家講LOD嘅時候,最好講清楚係LOD-G or LOD-I。

站於Client PM嘅角度,佢地好多時對LOD-G畫到有幾精細係唔會太關心,只要件嘢畫出嚟大概分辨到係啲乜就得;佢地真正關心嘅係件嘢係唔係跟足approved嘅物料嚟畫、畫得齊唔齊(如congested area嘅hangers)、夠唔夠空間運送、安裝及維修等等;至於LOD-I,就真係要入資料入得足,因為日後FM嘅同事真係要用到。

至於clashes方面,一般 Consultancy Agreement 或 Main Works Contract 的確係會寫死”Clashes Free” or “Zero Clashes”。至於撞5mm算係一個clashes,定係50mm先算係?暫時香港或國際用開嘅Standards or Guidelines都冇定義過,普遍做法會set 25mm ~ 50mm 之間。但站於工程項目PM嘅角度,佢地關心嘅唔係clashes個數字,而係落到場啲嘢係唔係真係夠位裝、夠位日後maintenance。筆者認為比較好嘅做法係,為呢堆clashes嘅重要程度分類,如下表﹕

Clashes CategoryDescription
1Design Issues需要顧問改設計先解決到嘅問題
2Coordination Issues判頭自己夾圖後可解決嘅問題,不涉及設計改動
3Modelling IssuesBIM modeller 手文之誤、或BIM軟件之問題,可簡單解決
最優先解決係1.,即係牽一髮會動全身嘅問題。有時為咗解決個clashes,係要改原有設計,可能又因為改完呢個設計,會有新clashes嘅出現,所以務必提前解決;至於歸類為2.及3.嘅clashes,一般留返比判頭自己解決就得。 至於5D, 6D, 7D, 8D…發展局好多年前已經決定棄用上述講法。原因係,5D以前(如 4D = Time,5D = Cost)有較好嘅共識,但5D以後係啲乜,幾乎無共識。所以發展局2017年第一封關於BIM嘅Technical Circular開始,甚至到最新嘅2023年Technical Circular,都係用20項BIM Uses嚟劃分個BIM究竟應該要點用﹕
BIM UsesDevB TC 2023
Design Stage
DevB TC 2023
Construction Stage
1Design AuthoringMandatoryMandatory
2Design ReviewsMandatoryMandatory
3Existing Conditions ModellingMandatoryMandatory
4Site AnalysisMandatoryN/A
53D CoordinationMandatoryMandatory
6Cost EstimationMandatoryMandatory
7Engineering AnalysisMandatoryMandatory
8Facility Energy AnalysisOptionalOptional
9Sustainability EvaluationMandatoryMandatory
10Space ProgrammingMandatoryN/A
11Phase Planning (4D Modelling)MandatoryMandatory
12Digital FabricationMandatoryMandatory
13Site Utilization PlanningN/AMandatory
143D Control and PlanningN/AMandatory
15As-Built ModellingN/AMandatory
16Project System AnalysisN/AOptional
17Maintenance SchedulingN/AMandatory
18Space Management and TrackingN/AOptional
19Asset ManagementN/AMandatory
20Drawing GenerationMandatoryMandatory
上述三個講法其實都已經包含咗响呢廿個BIM Uses入面。如LOD與3., 5., 15.~19.等有關;Clashes5.有關;5D同6.有關;其餘6D, 7D, 8D…即係一系列未有共識嘅BIM Uses。

DevB TC 2020年開始嘅BIM KPI,都只係以BIM Uses嚟劃分﹕ 一般嚟講,合約BIM Specification嘅BIM Uses會寫到好虛,舉一例,第14項 BIM Uses 嘅 3D Control and Planning,一般會咁寫﹕
"For a large-scale project requiring Digital Works Supervision System, the Contractor shall utilize the BIM model for digital setting-out, construction checking,
etc. as appropriate by means of 3D laser scanners, robotic total stations, etc. as far as practicable."

究竟個3D laser scanners要點用法?全個地盤任何setting out,包括開大墨、裝地渠、釘板留窿、砌牆...等等都要用?As far as practicable應該點理解?一個地盤咁多個位同時做緊嘢,而一台機幾十萬又要有受過專業訓練嘅人先識用,要求判頭成個地盤都用3D laser scanners又合唔合理? 抑或用嚟覆核一次墨斗哥哥條數已經算係做到呢個BIM Uses?

呢個時候,就係BIM Execution Plan BEP出場嘅時間。業主、顧問、判頭,可以基於地盤實際嘅需要,由判頭於BEP提出實現呢項BIM Uses嘅詳盡方法及應用範圍,然後上比顧問做approval,而呢份BEP就會以新嘅合約形式出現 (舊嘅合約係BIM Specification,新嘅合約係BEP;BEP係基於BIM Specification嘅原則而制定)。當然,BEP係一份 living document [1] 嚟,業主或顧問可以跟據實際情況要求判頭更新該文件並再次提交審批。


[1]: Living document is a document that is continually edited and updated.

沒有留言:

發佈留言